sticker shock

8th Street project estimated at $723,000

The Scott City Council’s thoughts of extending Eighth Street in order to provide another access to the Eastridge Addition were dealt a jolt on Tuesday evening during a Zoom meeting with their engineer.

The preliminary cost of street work, along with necessary water and sewer lines, has been estimated at $723,666, according to engineer David Frisch with GMS, Inc., Colorado Springs.

The council had previously received a bid of $111,095 to provide another access road into the subdivision from K96 Highway at Chestnut Street. However, there was also interest in exploring an extension of Eighth Street to Jefferson Street.

 

 

To read more please log in or subscribe to the digital edition https://etypeservices.com/Scott%20County%20RecordID659/

 